File #: 17-0086    Name: Award Contract STL405
Type: Action Item Status: Passed
In control: City Council
On agenda: 7/11/2017 Final action: 7/11/2017
Title: CONSIDERATION OF AWARDING A CONTRACT TO JUST CONSTRUCTION, INC. FOR THE CONSTRUCTION OF ADA CURB RAMPS AND REPLACEMENT OF THE CURB AND GUTTER CITYWIDE PROJECTS PROGRAM RESOLUTION NO. 2017-144 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS; AWARDING A CONTRACT FOR THE CONSTRUCTION OF ADA CURB RAMPS FY2014/2015 (STL405), ADA CURB RAMPS FY2016/2017 (STL415), AND REPLACEMENT OF THE CURB AND GUTTER PROGRAM CITYWIDE FY2015/16 (STL407) PROJECTS TO JUST CONSTRUCTION, INC., IN THE AMOUNT OF $783,996; APPROPRIATING $50,000 FROM THE AVAILABLE BALANCE OF THE TRAFFIC SIGNAL FUND TO STL405; AND APPROPRIATING $150,000 IN TRANSNET FUNDS FROM STL424 TO STL405 (4/5 VOTE REQUIRED)
Indexes: 4. Strong & Secure Neighborhoods
Attachments: 1. Item 12 - Attachment 1 - Original Contract & Appendicies (Mar 22 2017), 2. Item 12 - Attachment 2 - Disclosure Statement, 3. Item 12 - Attachment 3 - Addendum Signed 4-11-17, 4. Item 12 - Attachment 4 - Exhibit A - Loc Map (24x36), 5. Item 12 - Attachment 5 - Exhibit B-1, 6. Item 12 - Attachment 6 - Exhibit B-2, 7. Item 12 - Attachment 7 - Extension Letter, 8. Item 12 - Resolution

Title

CONSIDERATION OF AWARDING A CONTRACT TO JUST CONSTRUCTION, INC. FOR THE CONSTRUCTION OF ADA CURB RAMPS AND REPLACEMENT OF THE CURB AND GUTTER CITYWIDE PROJECTS PROGRAM

 

RESOLUTION NO. 2017-144 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS; AWARDING A CONTRACT FOR THE CONSTRUCTION OF ADA CURB RAMPS FY2014/2015 (STL405), ADA CURB RAMPS FY2016/2017 (STL415), AND REPLACEMENT OF THE CURB AND GUTTER PROGRAM CITYWIDE FY2015/16 (STL407) PROJECTS TO JUST CONSTRUCTION, INC., IN THE AMOUNT OF $783,996; APPROPRIATING $50,000 FROM THE AVAILABLE BALANCE OF THE TRAFFIC SIGNAL FUND TO STL405; AND APPROPRIATING $150,000 IN TRANSNET FUNDS FROM STL424 TO STL405 (4/5 VOTE REQUIRED)

 

Body

RECOMMENDED ACTION

Recommended Action  

Council adopt the resolution.

Body

SUMMARY

On April 19, 2017, the Director of Public Works received five (5) sealed bids for the Construction Project consisting of ADA Curb Ramps FY2014/2015 (CIP# STL405), ADA Curb Ramps FY2016/2017 (CIP# STL415) and Replacement of Curb and Gutter Program Citywide FY2015/16 (CIP# STL407) in the City of Chula Vista, California Project.  This project will install ADA pedestrian ramps: replace damaged curb, gutter and sidewalk; trim trees and prune roots damaging the sidewalk; all in various locations throughout the city; and construct certain intersection improvements at Third Avenue and Main Street.

 

ENVIRONMENTAL REVIEW

Environmental Notice

Environmental Notice

The Project qualifies for a Categorical Exemption pursuant to the California Environmental Quality Act State Guidelines Section 15301 Class 1 (Existing Facilities) and/or Section 15304 Class 4 (Minor Alterations to Land).

 

Body

Environmental Determination

The Director of Development Services has reviewed the proposed project for compliance with the California Environmental Quality Act (CEQA) and has determined that the project qualifies for a Categorical Exemption pursuant to State CEQA Guidelines Section 15301 Class 1 (Existing Facilities) and/or Section 15304 Class 4 (Minor Alterations to Land). Thus, no further environmental review is required. 

 

BOARD/COMMISSION RECOMMENDATION

Not Applicable

 

DISCUSSION

The project’s scope of work includes the installation of ADA pedestrian ramps where they are missing and replacement of damaged curb, gutter and sidewalk in various locations throughout the City.  The Project also includes tree trimming, root pruning and some tree removal; the replacement of a damaged inlet; and intersection improvements and traffic signal modifications at Third Avenue and Main Street.

 

On April 19, 2017, the Director of Public Works received five (5) bids as follows:

 

 

CONTRACTOR

BASE BID TOTAL

1

Just Construction Inc. - San Diego

$783,996.00

2

Pal General Engineering, Inc. - San Diego

$814,780.00

3

Tri-Group Construction & Development, Inc. - San Diego

$911,565.00

4

Wier Const. Corp.  -  Escondido

$933,352.00*

5

Blue Pacific Engineering and Construction - San Diego

$967,475.00*

* Minor mathematical errors reversed the order of the last two bidders

 

The low bid by Just Construction Inc. of $783,996.00 is $104,296 (approximately 15%) above the Engineer's estimate of $679,700.  

 

Just Construction, Inc. is a currently an active licensed Class “A”- General Engineering Contractor; Class “B”- General Building Contractor and Class “C-8”- Concrete (License No. 968910) and has performed similar work in the City with satisfactory performance. Staff has reviewed the bid submitted by Just Construction, Inc. and has determined it to be responsive. Just Construction, Inc. has provided the City with a letter dated May 24, 2017, stating that the contract amounts in their bid will valid through the end of July 2017 (see Attachment 1).  Therefore, staff recommends awarding the STL405, STL407 and STL415 project contract to Just Construction Inc.

 

Wage Statement

The Contractor and its subcontractors are required by bid specifications to pay prevailing wages (“Prevailing Wage Rates”) to persons employed by them for work under this Contract. In accordance with the provisions of Section 1773 of the Labor Code of the State of California, the City of Chula Vista has ascertained the general prevailing wage scales applicable to the work to be done. The prevailing wage scales are those determined by the Director of Industrial Relations, State of California.

 

Disclosure Statement

Attachment 2 is a copy of the Contractor’s Disclosure Statement.

 

DECISION-MAKER CONFLICT

Staff has reviewed the decision contemplated by this action and has determined that it is not site-specific and consequently, the 500-foot rule found in California Code of Regulations Title 2, section 18702.2(a)(11), is not applicable to this decision for purposes of determining a disqualifying real property-related financial conflict of interest under the Political Reform Act (Cal. Gov't Code § 87100, et seq.).

 

Staff is not independently aware, and has not been informed by any City Council member, of any other fact that may constitute a basis for a decision maker conflict of interest in this matter.

 

LINK TO STRATEGIC GOALS

The City’s Strategic Plan has five major goals: Operational Excellence, Economic Vitality, Healthy Community, Strong and Secure Neighborhoods and a Connected Community.  The installation of ADA Pedestrian Ramps and Replacement of Broken Curb, Gutter and Sidewalk supports the Strong and Secure Neighborhoods Strategic Goal as it maintains public infrastructure vital to the quality of life for residents.

 

CURRENT YEAR FISCAL IMPACT

Approval of the resolution will initiate the construction phase of STL405, STL407 & STL415 and appropriate $50,000 in Traffic Signal Funds to STL405 for work at Third Avenue and Main Street, and transfer $150,000 from STL424 to STL405.  Together, with the newly appropriated funds, sufficient TransNet and Gas Tax Funds are available to complete the project.  Therefore, there is no additional impact to these funds.

 

FUNDS REQUIRED FOR CONSTRUCTION

 

A. Contract Amount

 $783,996

B. Contingency

   $43,000

C. Construction Inspection Staff Cost

   $60,000

D. Construction Land Survey 

   $23,004

TOTAL FUNDS REQUIRED FOR CONSTRUCTION

 $910,000

 

ONGOING FISCAL IMPACT

Upon completion of the project, the improvements will require only routine City maintenance.

 

ATTACHMENTS

1.                     Contract Award Extension Letter

2.                     Contractor’s Disclosure Statement - Just Construction Inc.

3.                     Addendum

4.                     Exhibit A - Location Map

5.                     Exhibit B1 - Traffic Signal Modifications

6.                     Exhibit B2 - Traffic Signal Modifications

7.                     Extension Letter

 

Staff Contact: Mario Ingrasci, Associate Civil Engineer; Ext. 5476