Title: A. RESOLUTION NO. 2018-014 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS AND AWARDING A CONTRACT FOR THE "STREET PAVEMENT REHABILITATION - MEASURE P (CIP# STL0427)" PROJECT TO ATP GENERAL ENGINEERING CONTRACTORS, LLC. IN THE BID AMOUNT OF $5,127,997 B. RESOLUTION NO. 2018-015 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA AMENDING THE FY2017/18 CIP PROGRAM BUDGET BY ESTABLISHING NEW CIP PROJECTS, "STREET PAVEMENT REHAB PHASE II - MEASURE P (CIP# STL0430)" AND "CMP REHAB OUTSIDE RIGHT OF WAY PHASE II - MEASURE P (CIP# DRN0211)"; TRANSFERRING $8,750,000 IN MEASURE P APPROPRIATIONS FROM STL0427 TO STL0430; AND TRANSFERRING $5,639,000 IN MEASURE P APPROPRIATIONS FROM DRN0209 TO DRN0211 (4/5 VOTE REQUIRED)
Attachments: 1. Attachment 1 - Project Locations, 2. Attachment 2 - Disclosure Statement, 3. Resolution A, 4. Resolution B, 5. Presentation
Title
A. RESOLUTION NO. 2018-014 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS AND AWARDING A CONTRACT FOR THE "STREET PAVEMENT REHABILITATION - MEASURE P (CIP# STL0427)" PROJECT TO ATP GENERAL ENGINEERING CONTRACTORS, LLC. IN THE BID AMOUNT OF $5,127,997

B. RESOLUTION NO. 2018-015 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA AMENDING THE FY2017/18 CIP PROGRAM BUDGET BY ESTABLISHING NEW CIP PROJECTS, "STREET PAVEMENT REHAB PHASE II - MEASURE P (CIP# STL0430)" AND "CMP REHAB OUTSIDE RIGHT OF WAY PHASE II - MEASURE P (CIP# DRN0211)"; TRANSFERRING $8,750,000 IN MEASURE P APPROPRIATIONS FROM STL0427 TO STL0430; AND TRANSFERRING $5,639,000 IN MEASURE P APPROPRIATIONS FROM DRN0209 TO DRN0211 (4/5 VOTE REQUIRED)
Body
RECOMMENDED ACTION
Recommended Action
Council adopt the resolutions.
Body
SUMMARY
On December 20, 2017, the Director of Engineering and Capital Projects received five (5) sealed bids for the "Street Pavement Rehabilitation - Measure P (CIP# STL0427)" project. The project consists of routine rehabilitation of failed asphalt by milling and placing asphalt on all the street segments shown in Attachment 1. The proposed action would: (1) award the contract to ATP General Engineering Contractors, LLC, (2) create two new CIP projects, and (3) transfer available funds from two existing CIP projects (STL0427 & DRN0209) to the two new CIP projects.
ENVIRONMENTAL REVIEW

Environmental Notice
Environmental Notice
The Project qualifies for a Class 1(c) Categorical Exemption pursuant to Section 15301 (Existing Facilities) of the California Environmental Quality Act State Guidelines.

Body
Environmental Determination
The Director of Development Services has reviewed the proposed project for compliance with the California Environmental Quality Act (CEQA) and has determined that the project qualifies for a Class 1 Categorical Exemption pursuant to Section 15301(c) (Existing Facilities) of the State CEQA Guidelines. Thus, no further environmental...