city of Chula Vista

File #: 14-0726    Name: Storm Drain Rehabilitation FY 2013/2014
Type: Consent Item Status: Passed
In control: City Council
On agenda: 1/13/2015 Final action: 1/13/2015
Title: RESOLUTION NO. 2015-007 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS, AWARDING THE CONTRACT FOR THE "STORM DRAIN REHABILITATION FY 2013/2014 AT VARIOUS LOCATIONS IN THE CITY OF CHULA VISTA (DR193/DR196)" PROJECT TO TC CONSTRUCTION CO., IN THE AMOUNT OF $795,373, WAIVING CITY COUNCIL POLICY 574-01, AND AUTHORIZING THE EXPENDITURE OF ALL AVAILABLE CONTINGENCY FUNDS IN AN AMOUNT NOT TO EXCEED $80,000
Indexes: 4. Strong & Secure Neighborhoods
Attachments: 1. Item 7 - Attachment 1, 2. Item 7 - Resolution
Title
RESOLUTION NO. 2015-007 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS, AWARDING THE CONTRACT FOR THE "STORM DRAIN REHABILITATION FY 2013/2014 AT VARIOUS LOCATIONS IN THE CITY OF CHULA VISTA (DR193/DR196)" PROJECT TO TC CONSTRUCTION CO., IN THE AMOUNT OF $795,373, WAIVING CITY COUNCIL POLICY 574-01, AND AUTHORIZING THE EXPENDITURE OF ALL AVAILABLE CONTINGENCY FUNDS IN AN AMOUNT NOT TO EXCEED $80,000

Body
RECOMMENDED ACTION
Recommended Action
Council adopt the resolution.

Body
SUMMARY
On December 3, 2014, the Director of Public Works received nine (9) sealed bids for the "Storm Drain Rehabilitation FY 2013/2014 at various locations in the City of Chula Vista (DR193/DR196)" project. The project will rehabilitate portions of the City's storm drain system. The project includes the replacement and lining of existing corrugated metal pipe (CMP), installation of new drainage inlet frames and grates, and repair of an existing box culvert at various locations.

ENVIRONMENTAL REVIEW
The Development Services Director has reviewed the proposed project for compliance with the California Environmental Quality Act (CEQA) and has determined that the project qualifies for a Class 1 (c) categorical exemption pursuant to Section 15301 [Existing Facilities] of the State CEQA Guidelines because the project consists of the removal and replacement or rehabilitation of existing corrugated storm drain pipes at various locations in the City of Chula Vista involving negligible or no expansion of an existing use. Ancillary work will include replacement of asphalt surfaces, curbs and gutters as may be needed. Thus, no further environmental review is required.

BOARD/COMMISSION RECOMMENDATION
Not Applicable

DISCUSSION
Based on the results of inspections, including those performed with a closed circuit television camera, a number of existing corrugated metal pipes (CMP) conveying storm water runoff have been identified by the Public Works De...