Title: CONSIDERATION OF WAIVING IRREGULARITIES IN THE BID RECEIVED FOR THE "PAVEMENT MINOR REHABILITATION FY14/15 (SLURRY SEAL) (STL401)" PROJECT PER CITY CHARTER SECTION 1009 RESOLUTION NO. 2015-104 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS AND AWARDING A CONTRACT FOR THE "PAVEMENT MINOR REHABILITATION FY14/15 (SLURRY SEAL) (STL401)" PROJECT TO PAVEMENT COATINGS CO. IN THE AMOUNT OF $1,532,589.00; WAIVING IRREGULARITIES IN THE LOW BID RECEIVED; WAIVING CITY COUNCIL POLICY NO. 574-01; AND AUTHORIZING THE EXPENDITURE OF ALL AVAILABLE CONTINGENCY FUNDS IN AN AMOUNT NOT TO EXCEED $114,944
Attachments: 1. Item 9 - Attachment 1 - Street Segments and Plats.pdf, 2. Item 9 - Attachment 2 New Street Segments.pdf, 3. Item 9 - Attachment 3 - Letter dated April 16, 2015.pdf, 4. Item 9 - Attachment 4 - Disclosure Statement.pdf, 5. Item 9 - Resolution
Title
CONSIDERATION OF WAIVING IRREGULARITIES IN THE BID RECEIVED FOR THE "PAVEMENT MINOR REHABILITATION FY14/15 (SLURRY SEAL) (STL401)" PROJECT PER CITY CHARTER SECTION 1009

RESOLUTION NO. 2015-104 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA ACCEPTING BIDS AND AWARDING A CONTRACT FOR THE "PAVEMENT MINOR REHABILITATION FY14/15 (SLURRY SEAL) (STL401)" PROJECT TO PAVEMENT COATINGS CO. IN THE AMOUNT OF $1,532,589.00; WAIVING IRREGULARITIES IN THE LOW BID RECEIVED; WAIVING CITY COUNCIL POLICY NO. 574-01; AND AUTHORIZING THE EXPENDITURE OF ALL AVAILABLE CONTINGENCY FUNDS IN AN AMOUNT NOT TO EXCEED $114,944

Body
RECOMMENDED ACTION
Recommended Action
Council conduct the public hearing and adopt the resolution.

Body
SUMMARY
On April 15, 2015, the Director of Public Works received sealed bids for the "Pavement Minor Rehabilitation FY14/15 (Slurry Seal) (STL401)" project. The project consists of the removal and replacement of failed asphalt concrete pavement (dig-outs) and the application of Type II Rubber Polymer Modified Slurry (RPMS) seal on various streets in the City. Scope of work on this project also includes traffic control, striping and markings, additional signage and other miscellaneous items of work necessary to complete the project.

ENVIRONMENTAL REVIEW
The Development Services Director has reviewed the proposed project for compliance with the California Environmental Quality Act (CEQA) and has determined that the project qualifies for a Class 1(c) categorical exemption pursuant to Section 15301, Existing Facilities, of the State CEQA Guidelines. Thus, no further environmental review is necessary.

BOARD/COMMISSION RECOMMENDATION
Not Applicable

DISCUSSION
The Public Works Department utilizes a Pavement Management System (PMS) and pavement preservation program to develop the priority list of streets to rehabilitate and preserve throughout the city. This preservation program is designed to extend the roadway life and serviceabi...