city of Chula Vista

File #: 14-0681    Name:
Type: Consent Item Status: Passed
In control: City Council
On agenda: 12/16/2014 Final action: 12/16/2014
Title: RESOLUTION NO. 2014-249 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA AMENDING THE FISCAL YEAR 2014/2015 CIP BUDGET BY APPROPRIATING $200,620 FROM THE AVAILABLE BALANCE OF THE TDIF FUND AND $2,001,840 OF HIGHWAY BRIDGE PROGRAM (HBP) FUNDS BASED ON UNANTICIPATED REVENUE TO CIP NO. STL-384 (4/5 VOTE REQUIRED)
Attachments: 1. Item 10 - Attachment 1, 2. Item 10 - Resolution
Title
RESOLUTION NO. 2014-249 OF THE CITY COUNCIL OF THE CITY OF CHULA VISTA AMENDING THE FISCAL YEAR 2014/2015 CIP BUDGET BY APPROPRIATING $200,620 FROM THE AVAILABLE BALANCE OF THE TDIF FUND AND $2,001,840 OF HIGHWAY BRIDGE PROGRAM (HBP) FUNDS BASED ON UNANTICIPATED REVENUE TO CIP NO. STL-384 (4/5 VOTE REQUIRED)

Body
RECOMMENDED ACTION
Recommended Action
Council adopt the resolution.

Body
SUMMARY
By Resolution No. 2014-185 (See Attachment "1"), on October 14, 2014, the City Council awarded the Phase I - Willow Street Bridge Replacement (Water Line Relocation) [CIP No. STL-384, Federal Project No. BHLS-5203(016)] project, including Additive Alternate Bid Items, to TechCom International, Corporation in the amount of $3,520,358.40 and authorized a total expenditure of $4,411,330 for the project. A total of $1,815,850 has been appropriated as part of the normal Capital Improvement Project (CIP) process. However, supplemental appropriations in the amount of $2,202,460 are now necessary to provide the additional funds required to complete the Phase I project.

The proposed resolution, if approved, would appropriate $200,620 from the available balance of the Transportation Development Impact Fee (TDIF) funds and $2,001,840 of Highway Bridge Program (HBP) funds based on unanticipated revenue to CIP No. STL-384 in order to fully fund Phase I of this project.

ENVIRONMENTAL REVIEW
The Development Services Director has reviewed the proposed Project for compliance with the California Environmental Quality Act (CEQA) and has determined that the project was adequately covered in the previously adopted Mitigated Negative Declaration, IS-10-006 for the Chula Vista Willow Street Bridge Replacement Project on November 14, 2011. Thus, no further CEQA environmental review is required. In addition, the Development Services Director has reviewed the proposed project for compliance with the National Environmental Policy Act (NEPA) in conjunction with the Ca...

Click here for full text